You are the program manager for the NHQ Program. Your program has a budget of $4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?
Select the answer
1 correct answer
A.
The customer must now sign the program scope.
B.
The customer must now sign the payment for the program work.
C.
The customer must now sign the certificate of program closure.
D.
The customer must now sign the operational transfer agreement.

Quiz

2/10
Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?
Select the answer
1 correct answer
A.
Change requests
B.
Earned value management results
C.
Stakeholder analysis plan
D.
Performance reports

Quiz

3/10
What is the formula to determine earned value (EV) for a program?
Select the answer
1 correct answer
A.
Percent complete times percent remaining in the program
B.
Percent completes time the program cost estimate
C.
Percent complete times the program budget at completion
D.
Percent complete times the program cost of labor and materials

Quiz

4/10
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
Select the answer
1 correct answer
A.
Screening system
B.
Scoring model
C.
Vendor analysis requirements
D.
Evaluation criteria

Quiz

5/10
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
Select the answer
1 correct answer
A.
Requirements document
B.
Project charter
C.
Business case
D.
Scope statement

Quiz

6/10
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?
Select the answer
1 correct answer
A.
Quality control
B.
Scope verification
C.
Quality assurance
D.
Planning

Quiz

7/10
Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?
Select the answer
1 correct answer
A.
Teaming
B.
Exploiting
C.
Accepting
D.
Sharing

Quiz

8/10
A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?
Select the answer
1 correct answer
A.
Gold plating
B.
Errors and omissions
C.
Expert judgment by the project manager
D.
Value added change

Quiz

9/10
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?
Select the answer
1 correct answer
A.
Value-added change requests
B.
Zero based budgeting
C.
Integrated change control
D.
Gold plating

Quiz

10/10
What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?
Select the answer
1 correct answer
A.
Sensitivity analysis
B.
Stakeholder analysis
C.
Monte Carlo simulation
D.
Force field analysis
Looking for more questions?Buy now

PMI-PMI-PgMP Practice test unlocks all online simulator questions

Thank you for choosing the free version of the PMI-PMI-PgMP practice test! Further deepen your knowledge on PMI Simulator; by unlocking the full version of our PMI-PMI-PgMP Simulator you will be able to take tests with over 450 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 450 questions.

BUY NOW

What to expect from our PMI-PMI-PgMP practice tests and how to prepare for any exam?

The PMI-PMI-PgMP Simulator Practice Tests are part of the PMI Database and are the best way to prepare for any PMI-PMI-PgMP exam. The PMI-PMI-PgMP practice tests consist of 450 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The PMI-PMI-PgMP database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with PMI-PMI-PgMP Simulator will also give you an idea of the time it will take to complete each section of the PMI-PMI-PgMP practice test . It is important to note that the PMI-PMI-PgMP Simulator does not replace the classic PMI-PMI-PgMP study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the PMI-PMI-PgMP exam.

BUY NOW

PMI-PMI-PgMP Practice test therefore represents an excellent tool to prepare for the actual exam together with our PMI practice test . Our PMI-PMI-PgMP Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our PMI-PMI-PgMP Simulator and how our unique PMI-PMI-PgMP Database made up of real questions:

Info quiz:

  • Quiz name:PMI-PMI-PgMP
  • Total number of questions:450
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the PMI-PMI-PgMP exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our PMI-PMI-PgMP Simulator.

Use our Mobile App, available for both Android and iOS devices, with our PMI-PMI-PgMP Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all PMI-PMI-PgMP practice tests which consist of 450 questions and also provide study material to pass the final PMI-PMI-PgMP exam with guaranteed success. Our PMI-PMI-PgMP database contain hundreds of questions and PMI Tests related to PMI-PMI-PgMP Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW