The inputs of the Performance Reporting process include all of the following except for which one?
Select the answer
1 correct answer
A.
Performance reviews
B.
Work performance information
C.
Forecasted completion
D.
Performance measurements

Quiz

2/10
Which of the following does NOT assess the value a project brings to an organization?
Select the answer
1 correct answer
A.
Benefit cost analysis
B.
Net present value
C.
Value analysis
D.
Needs assessment

Quiz

3/10
Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?
Select the answer
1 correct answer
A.
Because each individual order is a "temporary endeavor," each order is a project.
B.
This is program management since there are multiple projects involved.
C.
This is a recurring process.
D.
Orders incurring revenue over $100,000 would be considered projects and would involve project management.

Quiz

4/10
A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project charter in this environment is to:
Select the answer
1 correct answer
A.
Create a project charter using brainstorming sessions with potential team members and stakeholders
B.
Create and present a draft project charter to potential team members and stakeholders to solicit their input.
C.
Create a project charter jointly with management for distribution to potential team members and stakeholders.
D.
Create a project charter with the functional managers and present it to the sponsor for signature.

Quiz

5/10
All of the following are correct statements about a project manager EXCEPT:
Select the answer
1 correct answer
A.
He or she is assigned after the project charter is created.
B.
He or she may initiate changes to the project.
C.
He or she manages changes and factors that create change.
D.
He or she is held accountable for project success or failure.

Quiz

6/10
A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the project manager should ask for help from:
Select the answer
1 correct answer
A.
The sponsor.
B.
Other project managers.
C.
The project management office.
D.
The team.

Quiz

7/10
While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk events. These adjustments are based on your past project experience when unknown risk events occurred and knocked the project off track. What should you do?
Select the answer
1 correct answer
A.
Include a management reserve in the budget to try to compensate for the unknown risks, and notify management to expect unknown risks to occur.
B.
Document the unknown risk items and calculate the expected monetary value based on probability and impact that may result from the occurrence.
C.
Determine the unknown risk events and the associated cost, then add the cost to the project budget as reserves.
D.
With the stakeholders, determine a percentage of the known risk budget to allocate to a management reserve budget.

Quiz

8/10
You are about to begin negotiations with people from another country. Which of the following should provide guidance on what business practices are allowed and not allowed?
Select the answer
1 correct answer
A.
The company code of conduct
B.
The project charter
C.
The scope management plan
D.
The negotiation plan

Quiz

9/10
An employee approaches you and asks to tell you something in confidence. He advises you that he has been performing illegal activities within the company for the last year. He is feeling guilty about it and is telling you in order to receive advice as to what he should do. What should you do?
Select the answer
1 correct answer
A.
Ask for full details.
B.
Confirm that the activity is really illegal.
C.
Inform your manager of the illegal activity.
D.
Tell the employee to inform his boss.

Quiz

10/10
What is one of the KEY objectives during contract negotiations?
Select the answer
1 correct answer
A.
Obtain a fair and reasonable price.
B.
Negotiate a price under the seller's estimate.
C.
Ensure that all project risks are thoroughly delineated.
D.
Ensure that an effective communications management plan is established.
Looking for more questions?Buy now

ISEB-ISEB-PM1 Practice test unlocks all online simulator questions

Thank you for choosing the free version of the ISEB-ISEB-PM1 practice test! Further deepen your knowledge on ISEB Simulator; by unlocking the full version of our ISEB-ISEB-PM1 Simulator you will be able to take tests with over 624 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 624 questions.

BUY NOW

What to expect from our ISEB-ISEB-PM1 practice tests and how to prepare for any exam?

The ISEB-ISEB-PM1 Simulator Practice Tests are part of the ISEB Database and are the best way to prepare for any ISEB-ISEB-PM1 exam. The ISEB-ISEB-PM1 practice tests consist of 624 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The ISEB-ISEB-PM1 database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with ISEB-ISEB-PM1 Simulator will also give you an idea of the time it will take to complete each section of the ISEB-ISEB-PM1 practice test . It is important to note that the ISEB-ISEB-PM1 Simulator does not replace the classic ISEB-ISEB-PM1 study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the ISEB-ISEB-PM1 exam.

BUY NOW

ISEB-ISEB-PM1 Practice test therefore represents an excellent tool to prepare for the actual exam together with our ISEB practice test . Our ISEB-ISEB-PM1 Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our ISEB-ISEB-PM1 Simulator and how our unique ISEB-ISEB-PM1 Database made up of real questions:

Info quiz:

  • Quiz name:ISEB-ISEB-PM1
  • Total number of questions:624
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the ISEB-ISEB-PM1 exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our ISEB-ISEB-PM1 Simulator.

Use our Mobile App, available for both Android and iOS devices, with our ISEB-ISEB-PM1 Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all ISEB-ISEB-PM1 practice tests which consist of 624 questions and also provide study material to pass the final ISEB-ISEB-PM1 exam with guaranteed success. Our ISEB-ISEB-PM1 database contain hundreds of questions and ISEB Tests related to ISEB-ISEB-PM1 Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW