1/10
Argument6
Which of the following project planning situations is the most frequent contributor to cost overruns?
Select the answer
1 correct answer
A.
lack of detailed planning for operational start-up
B.
Insufficient planning for change management
C.
Inappropriate definition of work breakdown structure
D.
Inadequate definition of scope at the estimate (budget) stage

Quiz

2/10
Argument7
Project delays are best analyzed
Select the answer
1 correct answer
A.
After either the contractor or the owner acknowledges ^responsibility for the delay.
B.
Contemporaneously with the delay.
C.
By an expert after the project is finished when complete records are available and the impact is known.
D.
Late in the project.

Quiz

3/10
Argument3
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Select the answer
1 correct answer
A.
8 days
B.
6 days
C.
4 days
D.
5 days

Quiz

4/10
Argument5
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours? Exam Dumps AACE-International-AACE-PSP AACE International AACE-International-AACE-PSP 3-2863216305
Select the answer
1 correct answer
A.
2 cranes
B.
1 crane
C.
4 cranes
D.
3 cranes

Quiz

5/10
Argument2
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002? Exam Dumps AACE-International-AACE-PSP AACE International AACE-International-AACE-PSP 5-3149264948
Select the answer
1 correct answer
A.
09-28-01.
B.
09-08-01.
C.
09-15-01.
D.
09-18-01.

Quiz

6/10
Argument1
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition? Exam Dumps AACE-International-AACE-PSP AACE International AACE-International-AACE-PSP 8-3149264948
Select the answer
1 correct answer
A.
After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
B.
After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
C.
After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Quiz

7/10
Argument0
If Activity E's duration changes to 4 months, what is the overall duration of the project. Exam Dumps AACE-International-AACE-PSP AACE International AACE-International-AACE-PSP 13-3003420097
Select the answer
1 correct answer
A.
19 months.
B.
20 months.
C.
22 months.
D.
21 months.

Quiz

8/10
Argument4
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
Select the answer
1 correct answer
A.
Use the progressed portion of the critical path of all the updates previous to the current update.
B.
Use the progressed portion of the critical path of the baseline schedule.
C.
Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
D.
Use the forward-looking critical path of the most current updates.

Quiz

9/10
Argument6
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
Select the answer
1 correct answer
A.
Acceleration.
B.
Production output.
C.
Productivity loss.
D.
Productivity efficiency.

Quiz

10/10
Argument7
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Select the answer
1 correct answer
A.
Not suitable for complicated projects with multiple planned critical paths.
B.
Accuracy is increased by inserting delaying events into the as-planned schedule.
C.
Not suitable for projects with long durations.
D.
Less accurate as the analysis advances through the project.
Looking for more questions?Buy now

AACE-International-AACE-PSP Practice test unlocks all online simulator questions

Thank you for choosing the free version of the AACE-International-AACE-PSP practice test! Further deepen your knowledge on AACE International Simulator; by unlocking the full version of our AACE-International-AACE-PSP Simulator you will be able to take tests with over 119 constantly updated questions and easily pass your exam. 98% of people pass the exam in the first attempt after preparing with our 119 questions.

BUY NOW

What to expect from our AACE-International-AACE-PSP practice tests and how to prepare for any exam?

The AACE-International-AACE-PSP Simulator Practice Tests are part of the AACE International Database and are the best way to prepare for any AACE-International-AACE-PSP exam. The AACE-International-AACE-PSP practice tests consist of 119 questions and are written by experts to help you and prepare you to pass the exam on the first attempt. The AACE-International-AACE-PSP database includes questions from previous and other exams, which means you will be able to practice simulating past and future questions. Preparation with AACE-International-AACE-PSP Simulator will also give you an idea of the time it will take to complete each section of the AACE-International-AACE-PSP practice test . It is important to note that the AACE-International-AACE-PSP Simulator does not replace the classic AACE-International-AACE-PSP study guides; however, the Simulator provides valuable insights into what to expect and how much work needs to be done to prepare for the AACE-International-AACE-PSP exam.

BUY NOW

AACE-International-AACE-PSP Practice test therefore represents an excellent tool to prepare for the actual exam together with our AACE International practice test . Our AACE-International-AACE-PSP Simulator will help you assess your level of preparation and understand your strengths and weaknesses. Below you can read all the quizzes you will find in our AACE-International-AACE-PSP Simulator and how our unique AACE-International-AACE-PSP Database made up of real questions:

Info quiz:

  • Quiz name:AACE-International-AACE-PSP
  • Total number of questions:119
  • Number of questions for the test:50
  • Pass score:80%

You can prepare for the AACE-International-AACE-PSP exams with our mobile app. It is very easy to use and even works offline in case of network failure, with all the functions you need to study and practice with our AACE-International-AACE-PSP Simulator.

Use our Mobile App, available for both Android and iOS devices, with our AACE-International-AACE-PSP Simulator . You can use it anywhere and always remember that our mobile app is free and available on all stores.

Our Mobile App contains all AACE-International-AACE-PSP practice tests which consist of 119 questions and also provide study material to pass the final AACE-International-AACE-PSP exam with guaranteed success. Our AACE-International-AACE-PSP database contain hundreds of questions and AACE International Tests related to AACE-International-AACE-PSP Exam. This way you can practice anywhere you want, even offline without the internet.

BUY NOW